For a confidential client, ARCO/Murray is currently constructing a wastewater pretreatment facility that includes two ~800,000-gallon sequencing batch reactor (SBR) tanks, a 450,000-gallon equalization tank, and a 127,000-gallon biomass holding tank. The 9,360 SF pump house and office facility is being delivered under a phased GMP approach, enabling early procurement of critical equipment and mobilization. ARCO/Murray also partnered with Second Order Controls to support system commissioning and I/O checkout. Scope includes all tank and pump piping, interior coatings, site grading, and paving.